Construction Schedule for the Week of August 29, 2022
The contractor will be finishing the work on Runway 8-26 this week, pulling wire and installing lights and signs in anticipation of the runway intersection closure. This will include
work immediately adjacent to Taxiway A, but only on the taxiway. Runway 8-26 and Taxiway B will be closed Monday morning, August 29 beginning at 6 a.m. Runway 8-26 will be
reopened for the Labor Day weekend, including all taxiway connectors, no later than 4 p.m., Friday, September 2.
Following the Labor Day weekend, beginning September 6 at 6 a.m., the runway intersection will be closed. Runway 8-26 will be completely closed. Runway 1-19 will be shortened
to 2,065 ft. with a displaced threshold south of the runway intersection.
Portions of Taxiway B, east of Runway 1-19 will remain closed for the weekend to facilitate construction, however, full use of Runway 8-26 will still be available.